Supplementary Estimate for the Procurement and Award of a New Housing Management IT System

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: Yes

Purpose:

This report provides a budgetary update in respect of the procurement and award of a new Integrated Housing Management IT System contract for a period of four years. The project is anticipated to cost c£600k. 

In order to commence the project in the current financial year a Housing Revenue Account (HRA) supplementary capital estimate of £160k and a virement of £240k from within existing 2020/21 HRA budgets is requested. Provision will be made in the 2021/22 Housing Revenue Account budget for the £200k balance.

Decision:

Cabinet

            RECOMMEND TO FULL COUNCIL

            The approval of a Housing Revenue Account supplementary estimate of £160k (which equates to a weekly rent of 92p per dwelling) for the costs associated with the procurement and implementation of a new integrated housing management IT system. 

Cabinet

            RESOLVED – That

           

(1)  the virement of £240k be approved from existing budgets - £140k from capital budget x 25 and £100k from revenue contingency underspend;

 

(2)  the procurement and award of a 2+1+1 Contract be approved to a total value of £500k (inclusive of maintenance and support costs_ of a new Integrated Housing Management System, subject to Full Council approving the above supplementary estimate;

 

(3)  the ongoing maintenance and support costs for the new system of £50k of which £15k is accounted for within existing budgets be noted.

Report author: Satnam Kaur

Publication date: 19/10/2020

Date of decision: 19/10/2020

Decided at meeting: 19/10/2020 - Cabinet

Effective from: 29/10/2020