Supplementary Estimate to Cover Costs Awarded Against the Council in Appeals - Y/103/18/PL and EP/148/20/PL - Karl Roberts - 10.30 am

Planning permission was refused for applications Y/103/18/PL and EP/148/20/PL. Both decisions were taken by the Development Control Committee (DCC) and were contrary to the advice of officers. In deciding the subsequent appeals, the Inspector has concluded that the Council acted unreasonably in refusing planning permission and has awarded costs against the Council.

 

This award follows an award of costs for BE/69/19/OUT in May 2020 (a decision also taken at DCC contrary to the officer recommendation). This award of costs (£11,400) was paid out of the Departments budget. A Supplementary Estimate is now sought to pay these further costs as the Department budget is unable to accommodate these significant additional payments.

 

Decision type: Non-key - Low

Decision status: Recommmend Forward to Council