Decision details

Habitat Banking - Update Report

Decision Maker: Policy and Resources Committee

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

This is an update report following the decision made by the Policy and Finance Committee on 8 July 2025 (to appoint a Habitat Banking Project Officer) and follows on from the updates made to members during the 12 March 2026 Policy and Resource Committee.

Decisions:

The Committee received a report from the Habitat Banking Officer providing an update on the council's Habitat Banking project and seeking approval to progress further work in relation to the Larksfield Recreation Ground.

 

          In presenting the report, the Habitat Banking Officer reminded Members that the Committee had previously received an update on habitat banking in March 2026, with a further written update provided at its last meeting held in July 2026. Since that time, Officers had completed three key pieces of work at Larksfield Recreation Ground, comprising a UK Habitat Survey, an Economic Feasibility Assessment and a programme of public consultation.

 

          The Committee was advised that the habitat survey had identified the creation of a moderate condition lowland meadow as the most suitable enhancement option for the site whilst retaining its existing recreational uses, including walking and dog walking. Subject to detailed design and implementation, the site was estimated to have the potential to generate approximately 17.04 Biodiversity Net Gain (BNG) units.

 

          Members were informed that the Economic Feasibility Assessment identified indicative costs of approximately £202,000. These costs included pre-commencement activity, habitat establishment, and the monitoring and management requirements associated with the mandatory 30 year maintenance period. Officers explained that approximately 6.2 BNG units, representing around 36% of the estimated total units available, would need to be sold to achieve a breakeven position based on current assumptions. Should all available units ultimately be sold, the assessment indicated a potential surplus of approximately £357,000, although Members were advised that these figures remained indicative and subject to further validation.

 

          The results of the public consultation were reported as generally positive, with support for biodiversity enhancement and the principle of establishing a habitat bank at Larksfield. Concerns raised during consultation principally related to the future use of the site, particularly the potential impact on dog walking and public access.

 

          The Committee was advised that North Bersted had been assessed as part of the habitat banking review but was not recommended for progression due to the extent of existing recreational use and the resulting limitations on habitat enhancement opportunities. Bersted Brooks remained a potential longer-term opportunity, although further ecological assessment and site investigation work would be required before any future decisions could be made.

 

          The Habitat Banking Officer advised that, based on the evidence gathered to date, the Larksfield Recreation Ground represented the most suitable site for further consideration. However, Members were not being asked to approve the establishment of a habitat bank at this stage. Instead, approval was sought to progress the next phase of work through the preparation of a Habitat Management and Monitoring Plan (HMMP) and further market testing of costs and financial assumptions. Members were advised that the HMMP would provide greater detail regarding habitat management arrangements, public access, dog walking considerations and long-term maintenance requirements. Further public engagement would also be undertaken before any final proposal was brought back to Committee for consideration.

 

          Officers confirmed that no additional funding was being sought at this stage, as the next phase of work would be funded from the existing Climate Change budget.

 

          Councillor Lawrence then proposed the recommendations as set out within the report which were seconded by Councillor Walsh.

 

          The Chair invited debate. Some Councillors referred to concerns expressed by local users regarding future access arrangements for dog walkers and queried whether maintaining public access could reduce the number of BNG units capable of being generated by the site. It was suggested that restricting access entirely might potentially increase the ecological value and associated income generation.

 

          In response, the Habitat Banking Officer advised that the intention was to explore how habitat enhancement and recreational use could coexist. He explained that the purpose of commissioning the HMMP was to determine the most appropriate management approach, including consideration of dog walking arrangements, whether dogs would need to be kept on leads, whether any fencing would be required, and how public access could be accommodated whilst achieving biodiversity objectives.

 

          One observation made was that it had taken considerable time for the complexities associated with Bersted Brooks and the local nature reserve designation to become fully apparent. A concern was raised regarding the long-term implications of habitat banking arrangements, including the role of Responsible Bodies, the legal status of conservation covenants and the extent of future council control over the land. Whilst acknowledging the potential financial benefits identified within the report, it was felt necessary to remain cautious regarding the long-term commitments associated with habitat banking and the importance of undertaking further market testing before reaching any final decision was emphasised.

 

          In response, the Habitat Banking Officer acknowledged the concerns raised and noted that habitat banking represented a relatively new area of work for the Council. Officers had been working with other local authorities to understand emerging best practice and lessons learned elsewhere. Members were advised that the proposed HMMP would provide detailed information regarding future management, monitoring and operational requirements over the 30 year period. Officers stressed that the council would not lose ownership or control of the land but would instead be formalising long-term habitat management arrangements. Any future proposal would be brought back to Committee before a final decision was sought.

 

          Councillor Lawrence, as the proposer of the recommendations, referred to comments contained within the consultation responses set out in Appendix 2 and highlighted what appeared to be contradictory references regarding fencing and public accessibility. Officers clarified that the comments formed part of the consultation feedback received from consultees and did not represent the Council's proposed design. Such matters would be explored and addressed through the HMMP process and future consultation exercises.

 

          There being no further comments, the Committee

 

                     RESOLVED  - that it

 

(1)             Approves to progress Larksfield Recreation Ground to the next stage of Habitat Bank development through the preparation of a Habitat Management and Monitoring Plan (HMMP).

 

(2)             Approves that further market testing is undertaken to validate habitat establishment costs, long-term management costs associated with establishing a Habitat Bank at Larksfield Recreation Ground.

 

(During the course of the discussion on this item, Councillor Greenway declared a Personal Interest as a Member of the Friends of Bersted Brooks Country Park).

 

 

Report author: William Page

Publication date: 30/10/2026

Date of decision: 22/10/2026

Decided at meeting: 22/10/2026 - Policy and Resources Committee